Heat goes on Clan Lab staff
The Pacific paradise of Fiji was no tropical holiday for members of
the Clan Lab team tasked with dismantling a vast methamphetamine operation
in Suva.

As part of Operation Outrigger/Lantern, four New Zealand Clan Lab team
members from Waikato, Auckland and Northland had to endure searing temperatures
and extremely dangerous conditions as part of their three-week task.

Operation Lantern/Outrigger involved a Malaysian-based transnational
crime group setting up one of the largest production houses in the
Southern Hemisphere with the potential to produce 1000kgs of ‘ice’ methamphetamine.
Early intelligence dating back to 2001 and close cooperation between
a number of police jurisdictions spanning Hong Kong, Fiji, the Philippines,
China, Malaysia, Indonesia, Australia and New Zealand resulted in the termination
of the organised crime group’s operations on 9 June this year.
Detective Senior Sergeant Dave Potaka, Intelligence Manager, says the
Clan Lab staff did a thoroughly professional job in extremely trying circumstances.
The staff worked with four New Zealand ESR scientists at the warehouse
site, which had notional hot, warm and cold zones – depending on the
level of danger or risk associated with different parts of the site.
“This job was particularly dangerous,” says Dave. “It was excessively
hot and the chemicals were not being kept in the most appropriate conditions.
Everything inside the warehouse was contaminated in some way by the chemicals
and process used.”
On a day-to-day basis, Clan Lab staff would start at 8am by airing
the warehouse for an hour while getting their kit together, making sure everything
was working and ensuring the local fire department was on site. Work would
finish at 5pm.
Through the day, the team would work for hour-long stretches and then
come out to open air to rest and replenish their fluids. Each time they came
out, the fire service washed them down as part of the decontamination process.
It was estimated each member was losing between 3 – 5 litres of fluids
each day, requiring them to drink up to 5 – 6 litres of water through
the day and topping up with more after work.
Among their tasks was the literal breaking down of the site and its
equipment, washing it and the double sampling of 130 40-gallon drums to determine
the chemicals in them. A large fibreglass ‘scrubber unit’ had
to be cut up for disposal, using a skill saw with a stone-tipped blade – all
in 35+ degree heat while wearing layers of protective clothing and breathing
apparatus.
When taking photos for exhibits staff had to keep a close eye on a
chemical metre to ensure the camera flash didn’t ignite the chemicals.
“But the attitude was very much one of let’s get on with this and get
things done,” says Dave. “Everyone knew each other’s capabilities,
they realised the dangers and knew they had a big job to do.”
Standard operating procedures were adapted due to the size of the operation
and an overall plan and daily plan were adhered to.
“They reasoned it all out and were totally focussed on what they were
doing. Admittedly, there were some grumpy times and we knew then it
was time for some time off.”
During the three weeks of dismantling, the team took two days off.
“Everyone was keen to get home,” says Dave
|